Lee Silk and Jack Plummer in our Dispute Resolution team have recently secured a favourable commercial settlement for a subcontractor in a complex construction payment and final account dispute.

The dispute arose between the subcontractor and main contractor following competing valuations of the subcontractor’s final account. The issues included:

· Payment applications and a disputed Pay Less Notice;

· Valuation of completed works and variations;

· Extensions of time;

· Construction loss and expense;

· Retention;

· Alleged delay and defects; and

· Counterclaims for additional preliminary costs.

Following detailed pre-action correspondence, our construction dispute solicitors entered into focused negotiations with the main contractor’s solicitors. Those negotiations substantially narrowed the difference between the parties’ positions and resulted in an agreed final account valuation on favourable terms for our client.

The settlement brought the construction dispute to an end without the need for adjudication or Court proceedings. This avoided the additional legal costs, management time and uncertainty associated with formal proceedings while securing a positive commercial outcome for the subcontractor.

The matter demonstrates the importance of maintaining clear project records throughout construction works. Payment applications, Pay Less Notices, programmes, variation records, site correspondence and evidence of delay can all be important when resolving a construction payment dispute.

The dispute portrayed the value of combining detailed contractual analysis with practical commercial negotiation. Although construction adjudication can provide a fast route to a binding decision, a properly prepared negotiation may enable the parties to resolve payment, final account and delay issues more efficiently.

Our Dispute Resolution team advises contractors, subcontractors, developers and construction professionals on matters including:

· Construction payment disputes;

· Final account and valuation disputes;

· Payment notices and Pay Less Notices;

· Extensions of time and loss and expense claims;

· Variations and additional works;

· Retention and defective works;

· Construction adjudication; and

· Commercial negotiation and settlement.

If you require advice concerning a construction payment dispute, final account, Pay Less Notice or proposed adjudication, please contact our Dispute Resolution team at disputeresolution@curzongreen.co.uk.